REPORT OF THE
COMMITTEE ON CONSTRUCTION
The Honorable,
The Board of Commissioners of
ATTENDANCE
|
Present: |
Chairman Murphy, Commissioners Beavers, Schneider,
Silvestri and Sims (5) |
|
Absent: |
Vice Chairman Butler, Commissioners Gorman, |
|
Also
Present: |
Bruce Washington - Director, Office of Capital Planning
and Policy |
Ladies and
Gentlemen:
Your Committee
on Construction of the Board of Commissioners of Cook County met pursuant to
notice on
Your Committee
has considered the following items and upon adoption of this report, the
recommendations are as follows:
|
287207 |
OFFICE OF CAPITAL PLANNING AND POLICY, by Bruce
Washington, Director, transmitting a Communication, dated Transmitted herewith for your approval is Change Order No.
4 to the contract with FHP TECTONICS
CORPORATION, Contractor for the Countywide Americans with Disabilities
Act (ADA) Study & Renovations, Phase II.
It is respectfully requested that this Honorable Body approve this
request. Reason: This
change order provides for the allowance of additional contract time that is
necessary to compensate the Contractor for delays to their work caused by
conditions outside of their control. A
total time extension of 109 days is requested. Contract No. 04-53-717 Original
Contract Sum: $4,474,000.00 Total
Changes to-date: 67,618.05 Adjusted
Contract to-date: $4,541,618.05 Amount
of this Modification: 0.00 Adjusted
Contract Sum: $4,541,618.05 Estimated Fiscal Impact:
None. Contract extension: 109 days. * Referred to the Construction Committee on |
|
287208 |
OFFICE OF CAPITAL PLANNING AND POLICY, by Bruce
Washington, Director, transmitting a Communication, dated Transmitted herewith for your approval is Change Order No.
6 to the contract with FHP TECTONICS
CORP., Contractor for the Reason: This
change order provides for modifications necessary to attach the new screen
wall onto the roof. Also, as part of
the new generator work, upgrading of the emergency power in the north and
south elevator banks is required. A
time extension of 25 days is requested for this additional work. Contract No. 05-53-401 Original
Contract Sum: $5,047,000.00 Total
Changes to-date: 159,786.47 Adjusted
Contract to-date: $5,206,786.47 Amount
of this Modification: 59,784.08 Adjusted
Contract Sum: $5,266,570.55 Estimated Fiscal Impact:
$59,784.08. Contract
extension: 25 days. Bond Issue (7000 Account). * Referred to the Construction Committee on |
Commissioner
Silvestri, seconded by Commissioner Schneider, moved the approval of
Communication Numbers 287207 and 287208. The motion carried.
Chairman Murphy asked the Secretary to the Board to call
upon the registered public speakers.
1. George
Blakemore, Concerned Citizen
Commissioner Silvestri
moved to adjourn the meeting, seconded by Commissioner Sims. The motion carried and the meeting was
adjourned.
YOUR COMMITTEE
RECOMMENDS THE FOLLOWING ACTION WITH REGARD TO THE MATTERS NAMED HEREIN:
Communication
Number 287207 Approved
Communication
Number 287208 Approved
|
|
Respectfully
submitted, Committee
on Construction xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx Joan
Patricia Murphy, Chairman |
Attest:
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
Matthew B.
DeLeon, Secretary
** The audio recording for this meeting is available from
the Office of the Secretary to the Board,