REPORT OF THE COMMITTEE ON CONSTRUCTION

 

January 30, 2008

 

The Honorable,

The Board of Commissioners of Cook County

 

ATTENDANCE

 

Present:

Chairman Murphy, Vice Chairman Butler, Commissioners Gorman, Silvestri, Sims and Steele (6)

 

Absent:

Commissioners Beavers, Moreno and Schneider (3)

 

Also Present:

Elizabeth Melas – Deputy Director, Office of Capital Planning and Policy; Zelda Whittler – Undersheriff, Office of the Sheriff.

 

Ladies and Gentlemen:

 

        Your Committee on Construction of the Board of Commissioners of Cook County met pursuant to notice on Wednesday, January 30, 2008 at the hour of 11:00 AM in the Board Room, Room 569, County Building, 118 North Clark Street, Chicago, Illinois.

 

        Your Committee has considered the following items and upon adoption of this report, the recommendations are as follows:

 

291502

OFFICE OF CAPITAL PLANNING AND POLICY, by Bruce Washington, Director, transmitting a Communication, dated December 17, 2007:

 

Transmitted herewith for your approval is a request for authorization to enter into a professional services contract with ROULA ASSOCIATES ARCHITECTS, CHTD., Chicago, Illinois, selected from the Request for Qualifications/Proposals process.  The services required are design and construction administration for the Residential Treatment Unit - Reception Classification Diagnostic Center (RTU-RCDC) Project at the Department of Corrections.  It is respectfully requested that this Honorable Body approve this request.

 

Reason:     This project will provide a new facility to combine and house the Department of Corrections Reception Classification Diagnostic Center (RCDC or intake facility) which processes admissions into the Department of Corrections (DOC) and Cermak Health Services of Cook County and a Residential Treatment Unit (RTU).  The program includes new intake, holding, and processing areas, clinics, medical services and associated administrative functions, dormitories and auxiliary dormitory functions.  In recent years, this system has had to respond to the demands of increasing numbers of inmate admissions and mental health evaluations and treatment.  The existing RCDC and RTU facilities can no longer accommodate the volume of admissions, screenings and care required.  The facilities are overcrowded, basic amenities are inadequate, building systems are outdated and in some cases non-functional.

 

                  The new facility will meet current “Essential Standards” set by the National Commission on Correctional Health Care and the American Correctional Association which are required for maintaining accreditation, and will provide for an efficient and orderly intake process including screening and provision of care.

 

Estimated Fiscal Impact:  $4,300,000.00.  Bond Issue (20000 Account).

 

Sufficient funds have been appropriated to cover this request.

 

*Referred to the Committee on Construction on 01/09/08.

 

Vice Chairman Butler, seconded by Commissioner Steele, moved the approval of Communication No. 291502. The motion carried.

 

291503

OFFICE OF CAPITAL PLANNING AND POLICY, by Bruce Washington, Director, transmitting a Communication, dated December 17, 2007:

 

Transmitted herewith for your approval is a request for authorization to enter into a professional services contract with HOH SYSTEMS, INC., Chicago, Illinois, selected from the Request for Qualifications/Proposals process.  The services required are design and construction administration for the Courthouse Server Consolidation project.  It is respectfully requested that this Honorable Body approve this request.

 

Reason:     This project will allow the Bureau of Information Technology & Automation to locate centralized server farms in each of our main courthouses with the appropriate environmental elements, which will be backed-up automatically over the Wide Area Network.  This consolidated server farm will be highly secure, with cameras and located racks.  The 2nd, 3rd, 4th, 5th and 6th District courthouses will be included in this project.

 

Estimated Fiscal Impact:  $350,000.00.  Bond Issue (20000 Account).

 

Sufficient funds have been appropriated to cover this request.

 

*Referred to the Committee on Construction on 01/09/08.

 

Vice Chairman Butler, seconded by Commissioner Steele, moved the approval of Communication No. 291503. The motion carried.

 


 

291504

OFFICE OF CAPITAL PLANNING AND POLICY, by Bruce Washington, Director, transmitting a Communication, dated December 17, 2007:

 

Transmitted herewith for your approval is a request for authorization to enter into a professional services contract with GLOBETROTTERS ENGINEERING CORPORATION, Chicago, Illinois, selected from the Request for Qualifications/Proposals process.  The services required are design and construction administration for the Juvenile Temporary Detention Center HVAC Upgrade.  It is respectfully requested that this Honorable Body approve this request.

 

Reason:    This project will replace and upgrade HVAC systems at the Juvenile Temporary Detention Center West and East Buildings.  The work includes converting the existing chiller/heater absorber HVAC system into a separate boiler and chiller system to provide energy efficient heating and cooling to the west addition.  It also includes the replacement and upgrade of fan coil units and chilled water valves and pneumatic controls for the East portion of the building.  Electrical upgrades as required to adequately handle all HVAC equipment are included.

 

Estimated Fiscal Impact:  $280,000.00.  Bond Issue (32000 Account).

 

Sufficient funds have been appropriated to cover this request.

 

*Referred to the Committee on Construction on 01/09/08.

 

Vice Chairman Butler, seconded by Commissioner Gorman, moved the approval of Communication No. 291504. The motion carried.

 

291505

OFFICE OF CAPITAL PLANNING AND POLICY, by Bruce Washington, Director, transmitting a Communication, dated December 17, 2007:

 

Transmitted herewith for your approval is a request for authorization to enter into a professional services contract with DELTA ENGINEERING, INC., Chicago, Illinois, selected from the Request for Qualifications/Proposals process.  The services required are design and construction administration for the HVAC Upgrade for Buildings 3 and 4 located at the South Campus at the Department of Corrections.  It is respectfully requested that this Honorable Body approve this request.

 

Reason:     Currently only Building 3 has central air conditioning on floor 1 and part of floor 2, and the air conditioning unit is defective.  All other air conditioning in the buildings is provided by window units. The units are a security risk in that they can be removed by detainees for egress or dissembled for parts.  The provision of central air conditioning throughout the two buildings will eliminate this security risk and provide more efficient climate control and energy conservation.

 

Estimated Fiscal Impact:  $250,000.00.  Bond Issue (20000 Account).

 

Sufficient funds have been appropriated to cover this request.

 

*Referred to the Committee on Construction on 01/09/08.

 

Commissioner Gorman, seconded by Commissioner Steele, moved the approval of Communication No. 291505. The motion carried.

 

291506

OFFICE OF CAPITAL PLANNING AND POLICY, by Bruce Washington, Director, transmitting a Communication, dated December 17, 2007:

 

Transmitted herewith for your approval is a request for authorization to enter into a professional services contract with ONYX ARCHITECTURAL SERVICES, INC., Chicago, Illinois, selected from the Request for Qualifications/Proposals process.  The services required are design and construction administration for the Countywide Roof Replacement, Phase IV project.  It is respectfully requested that this Honorable Body approve this request.

 

Reason:    This project is for architectural services for the renovation of several roofs and will consist of complete tear-off and roof replacement of 118 North Clark Street, Criminal Courts Administration Building, Oak Forest Hospital of Cook County Powerhouse, Oak Forest Hospital of Cook County New E Building, Oak Forest Hospital of Cook County Building B, Oak Forest Hospital of Cook County Administration Building, Oak Forest Hospital of Cook County Store Room #23 and the Oak Forest Hospital of Cook County Lab and Morgue.

 

Estimated Fiscal Impact:  $200,000.00.  Bond Issue (20000 Account).

 

Sufficient funds have been appropriated to cover this request.

 

*Referred to the Committee on Construction on 01/09/08.

 

Vice Chairman Butler, seconded by Commissioner Steele, moved the approval of Communication No. 291506. The motion carried.

 

Chairman Butler asked the Secretary to the Board to call upon the registered public speaker.

 

1)         George Blakemore – Concerned Citizen

 

 

Commissioner Gorman moved to adjourn the meeting, seconded by Commissioner Silvestri.  The motion carried and the meeting was adjourned.

 


YOUR COMMITTEE RECOMMENDS THE FOLLOWING ACTION

WITH REGARD TO THE MATTER NAMED HEREIN:

 

                        Communication Number 291502                                           Approved

                        Communication Number 291503                                           Approved

                        Communication Number 291504                                           Approved

                        Communication Number 291505                                           Approved

                        Communication Number 291506                                           Approved

 

 

 

Respectfully submitted,

Committee on Construction

 

 

 

xxxxxxxxxxxxxxxxxxxxxxxxxxxxx

Joan Patricia Murphy, Chairman

 

Attest:

 

 

 

xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx

Matthew B. DeLeon, Secretary

 

 

 

** The audio recording for this meeting is available from the Office of the Secretary to the Board, 118 North Clark Street, Room 567, Chicago, IL 60602.