REPORT OF THE COMMITTEE ON ROADS AND BRIDGES

 

January 9, 2007

 

The Honorable,

The Board of Commissioners of Cook County

 

ATTENDANCE

 

Present:

President Stroger, Chairman Moreno, Commissioners Beavers, Butler, Claypool, Collins, Daley, Goslin, Maldonado, Murphy, Peraica, Quigley, Schneider, Silvestri, Steele, and Suffredin  (15)

 

Absent:

Vice Chairman Gorman and Commissioner Sims (2)

 

Ladies and Gentlemen:

 

Your Committee on Roads and Bridges, having had under consideration the matters hereinafter mentioned, respectfully reports and recommends as follows:

 

Section 1

 

Your Committee has considered the following communications from Rupert Graham, Jr. P.E., the Acting Superintendent of Highways, recommending for approval of the change in plans and extra work involved in the construction of certain highway improvements as described:

 

283667

COUNTY HIGHWAY DEPARTMENT, by Wally S. Kos, P.E., Superintendent of Highways, submitting recommendation for change in plans and extra work on Section:  05-TSCMC-04-TL.  Traffic Signal Modernization 2005.  Various locations.  Adjustment of quantities and new items.  $52,226.90 (Deduction).

 

283668

COUNTY HIGHWAY DEPARTMENT, by Wally S. Kos, P.E., Superintendent of Highways, submitting recommendation for change in plans and extra work on Section:  02-TSCMC-03-TL.  Traffic Signal Modernization.  Nineteen (19) locations in County Board Districts #14, 15 and 17.  Adjustment of quantities and new item.  $852.54 (Deduction).

 

283669

COUNTY HIGHWAY DEPARTMENT, by Wally S. Kos, P.E., Superintendent of Highways, submitting recommendation for change in plans and extra work on Section:  03-A6201-01-FP.  Shoe Factory Road, Kane County Line to Prestbury Drive in the Villages of Elgin and Hoffman Estates in County Board District #15.  New items.  $69,693.50 (Addition).

 

283670

COUNTY HIGHWAY DEPARTMENT, by Wally S. Kos, P.E., Superintendent of Highways, submitting recommendation for change in plans and extra work on Section:  04-B5332-02-CH.  138th Street at Halsted Street in the Village of Riverdale in County Board District #5.  Adjustment of quantities and new items.  $26,336.05 (Addition).

 

 

 

 

283671

COUNTY HIGHWAY DEPARTMENT, by Wally S. Kos, P.E., Superintendent of Highways, submitting recommendation for change in plans and extra work on Section:  97-B5014-01-PV.  Federal Project No. M-7003 (851).  State Job No. C-91-070-00.  Contract No. 10211.  127th Street, State Street to Archer Avenue in the Village of Lemont in County Board District #17.  Adjustment of quantities and new items.  $25,157.23 (Deduction).

 

Commissioner Goslin, seconded by Commissioner Silvestri, moved the approval of Communication Nos.  283667, 283668, 283669, 283670 and 283671.  The motion carried unanimously.

 

 

Commissioner Maldonado, seconded by Commissioner Silvestri moved to adjourn the meeting. The motion carried and the meeting was adjourned.

 

 

 

Respectfully submitted,

Committee on Roads and Bridges

 

 

xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx

Joseph Mario Moreno, Chairman

 

 

Attest:

 

 

xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx

Matthew B. DeLeon, Secretary