REPORT OF THE COMMITTEE ON ROADS AND
BRIDGES
The Honorable,
The Board of Commissioners of
ATTENDANCE
|
Present: |
President Stroger and Chairman
Moreno, Vice Chairman Gorman, Commissioners Beavers, |
|
Absent: |
Commissioner Collins, Goslin,
Maldonado and Sims (4) |
Your Committee on Roads and Bridges,
having had under consideration the matters hereinafter mentioned, respectfully
reports and recommends as follows:
Section 1
Your Committee has considered the following communications
from Rupert Graham, Jr. P.E., the Acting Superintendent of County Department of
Highways, recommending for approval of the change in plans and extra work involved
in the construction of certain highway improvements as described:
|
284412 |
COUNTY HIGHWAY DEPARTMENT, by Rupert F. Graham, Jr., P.E., Acting Superintendent of Highways,
submitting recommendation for change in plans and extra work on Section: 01-W4612-05-BR. Group 6-2001: |
|
284413 |
COUNTY HIGHWAY DEPARTMENT, by Rupert F. Graham, Jr.,
Acting Superintendent of Highways, submitting recommendation for change in
plans and extra work on Section:
06-8PVMK-29-GM. Pavement
Markings - 2006. Final adjustment of
quantities. $266,901.81 (Deduction). |
Vice Chairman Gorman, seconded by Commissioner Steele, moved the
approval of the change in plans and extra work
described in Communication
Nos. 284412 and 284413. The motion
carried unanimously.
Section 2
Your Committee has considered the bids submitted on the item
hereinafter described in accordance with the specifications prepared by the Acting
Superintendent of the County Department of Highways.
Your Committee has considered the communications from the Acting
Superintendent of the County Department of Highways, submitting recommendations
on the award of contracts for said item, and recommends that the contract be
and upon the adoption of this Report, awarded as follows:
1)
(REBID/REVISED)
Section 04-B8431-08-PV
Federal Project
No. M-8003-(427)
Job No. C-91-278-04
In the Villages of East Hazel Crest,
Hazel Crest
and
Motor Fuel Tax Fund (600-600 Account)
Contract awarded to: Albin Carlson &
Company $13,089,028.80
The deposit checks are ordered returned to the unsuccessful
bidders at once and to the successful bidder upon the signing of the contract.
Vice Chairman Gorman, seconded by Commissioner Steele, moved to concur
with the recommendation in awarding the contract. The motion carried unanimously.
Commissioner
Claypool, seconded by Commissioner Butler moved to adjourn the meeting. The
motion carried and the meeting was adjourned.
|
|
Respectfully submitted, Committee on Roads and Bridges xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx Joseph Mario Moreno, Chairman |
Attest:
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
Matthew B. DeLeon, Secretary