Section 1
Your Committee has considered the
following communication from Rupert F. Graham, Jr., P.E., Superintendent of Highways, recommending for
approval change in plans and extra work in the construction of certain highway
improvements.
|
298139 |
COUNTY HIGHWAY DEPARTMENT, by Rupert
F. Graham, Jr., P.E., Superintendent of Highways, submitting recommendation
for change in plans and extra work on Section: 07-B6526-01-FP. |
|
298140 |
COUNTY HIGHWAY DEPARTMENT, by Rupert
F. Graham, Jr., P.E., Superintendent of Highways, submitting recommendation
for change in plans and extra work on Section: 08-B5935-05-RP. 170th (167th) Street, east of Bishop Ford
Expressway (I-94) to Burnham Avenue in the Villages of Lansing and South
Holland in County Board District #6.
Adjustment of quantity.
$99,904.00 (Addition). |
|
298141 |
COUNTY HIGHWAY DEPARTMENT, by Rupert F. Graham, Jr., P.E.,
Superintendent of Highways, submitting recommendation for change in plans and
extra work on Section:
08-B8526-03-RS. Oak Forest
Avenue, Ridgeland Avenue to 167th Street in the Village of Tinley Park and
the Forest Preserve District of Cook County in County Board District
#17. Adjustment of quantities. $176.50 (Deduction). |
|
298142 |
COUNTY HIGHWAY DEPARTMENT, by Rupert F. Graham, Jr., P.E.,
Superintendent of Highways, submitting recommendation for change in plans and
extra work on Section:
01-W3019-05-RP. 88th Avenue,
87th Street to 79th Street in the City of Hickory Hills and the Village of
Justice in County Board Districts #16 and 17.
Adjustment of quantities and new item. $16,111.27 (Addition). |
|
298143 |
COUNTY HIGHWAY DEPARTMENT, by Rupert F. Graham, Jr., P.E.,
Superintendent of Highways, submitting recommendation for change in plans and
extra work on Section: 04-B8431-08-PV.
Federal Project No. CMM-HPD-M8003-(427). State Job No. C-91-278-04. Contract No. 10212. 171st Street, Wood Street to Ashland Avenue
in the City of Harvey and the Villages of East Hazel Crest and Hazel Crest in
County Board Districts #5 and 6.
Adjustment of quantities and new items. $299,467.20 (Deduction). |
|
298144 |
COUNTY HIGHWAY DEPARTMENT, by Rupert F. Graham, Jr., P.E.,
Superintendent of Highways, submitting recommendation for change in plans and
extra work on Section:
06-B5928-02-RP. 167th Street, Kilbourn Avenue to Park Avenue in the Villages of Country
Club Hills, Hazel Crest, Markham and Oak Forest in County Board Districts #5
and 6. Final adjustment of
quantities. $251,493.87 (Deduction). |
Commissioner Murphy,
seconded by Commissioner Sims, moved the Approval of the change in plans and extra work described in Communication Nos. 298139, 298140, 298141, 298142, 298143 and 298144.
The motion carried unanimously.
Section 2
Your
Committee has considered the following items and upon adoption of this report,
the recommendations are as follows:
|
298145 |
COUNTY HIGHWAY DEPARTMENT, by Rupert F. Graham, Jr., P.E.,
Superintendent of Highways, submitting the Bureau of Construction's Progress
Report for the month ending |
Commissioner Murphy,
seconded by Commissioner Sims moved to Receive and File Communication No. 298145. The motion carried unanimously.
Section 3
Your Committee has considered the
bids submitted on the item hereinafter described in accordance with the
specifications prepared by the
Your Committee has considered the
communication from the Superintendent of Highways, submitting recommendations
on the award of contract for said items, and recommends that the contract be
and upon the adoption of this Report, awarded as follows:
Section 85-W8140-01-RP
Cities of DesPlaines and
County
Board District Nos. #9 and #17
Motor Fuel Tax Account #600-600
Contract awarded to: Martam
Construction, Inc. $11,175,672.20
The deposit checks are ordered
returned to the unsuccessful bidders at once and to the successful bidder upon
the signing of the contract.
Commissioner Murphy, seconded by Commissioner Sims, moved to award the
above referenced contract. The motion
carried unanimously.
Commissioner Murphy moved to adjourn, seconded by Commissioner Sims. The
motion carried and the meeting was adjourned.
|
|
Respectfully
submitted, Committee on
Roads and Bridges xxxxxxxxxxxxxxxxxxxxxxxxxxxxxx Joseph Mario
Moreno, Chairman |
Attest:
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
Matthew B. DeLeon, Secretary